Use the data below to create a network diagram and identify the critical path. What will be the total project duration?
Use the excel file for your submission.
|
Task |
Duration |
Predecessor |
|
A |
5 |
Start |
|
B |
8 |
A |
|
C |
3 |
B |
|
D |
4 |
A |
|
E |
5 |
C |
|
F |
7 |
C |
|
G |
6 |
D,E |
|
H |
8 |
F |
|
I |
6 |
G |
|
J |
4 |
H,I |