Albion International School engages Robert to build a new Olympic size swimming pool in the sports complex.
Need help with this assignment?Get an original answer from a qualified tutor — from $10/page.
Get it written →Albion International School engages Robert to build a new Olympic size swimming pool in the
sports complex. The agreed price is $5 million for the pool and $1.5 million for the tiling works.
For the tiles to be used in the spectator stands, AIS chose Granada Azure 8-43. The completed
swimming pool has a length of 49.92m; its depth at the ends is 1.8m rather than the stipulated
1.55m. For tiles, Robert used Granada Aqua 8-45 instead of what AIS selected. The cost of
rectifying the pool is $4 million while the cost of retiling is $2 million. The diminution in the
market value of the property is estimated to be $500,000.
AIS demands that Robert rectify the defects. Robert does not wish to carry out rectification
works but is willing to take 15% less than the contract price. Will AIS succeed in its claim?
Get a plagiarism-free answer to this question
Send us your instructions and we’ll match you with the best writer in your subject.
- 100% human-written, zero AI
- Turnitin report included
- Confidential — we never share your data
- Free revisions & refunds