Develop the MRP for all of the components
The Casual Furniture Company
The Casual Furniture Company (CFC) makes a variety of bookshelves for homes and businesses. The shelves come in various heights, widths, materials, and finishes. Effective requirements planning is essential for CFC’s performance, and it uses MRP for planning.
The MPS and MRP records are shown for one of CFC’s products, part number 4 × 3-01, a four-foot-high and three-foot-wide standard depth oak bookshelf. The BOM as a product structure diagram is shown in Figure 14-19.
FIGURE 14-19 Bookshelf 4 × 3-01 BOM
A diagram of a book shelf Description automatically generated
CFC uses one-week time buckets and a planning horizon of eight weeks. The MPS for the 4 × 3-01 Bookshelf is shown in Figure 14-20.
FIGURE 14-20 MPS Bookshelf 4 × 3-01
A close up of a number Description automatically generatedTable Summary: Summary
The cabinets are built in the cabinet assembly department and the shelves, backs, sides, and ends are made in the cutting department. The component lot size, lead time, available inventory and safety stock are shown in Figure 14-21. Two associates work in the cutting department, making the available capacity 80 hours per week, without overtime. The processing time for each component in the cutting department is shown in Figure 14-22. Also note that there is a scheduled receipt of 600 brackets in week 1 and a scheduled receipt of 1000 oak sheets in week 1.
FIGURE 14-21 Component Lot Size and Inventory Information
FIGURE 14-22 Cutting Department Processing Time
A close-up of a white and blue sign Description automatically generated with medium confidence
Questions
1) Develop the MRP for all of the components.
2) During week 1 of the plan, the bracket supplier notifies CFC that the order for 600 units will not arrive as planned. Instead, 300 will arrive this week and 300 will arrive next week, instead of all 600 arriving at the same time. Will this affect production and, if so, to what extent?
3) Now that the plan has been developed, is it feasible to consider the capacity of the cutting department? What recommendations do you have?
4) If you could change the lead times or lot-sizing policies used for any of the components, what changes would you make? Why?
THIS SHOULD BE BASED ON BOOK: Managing Operations Across the Supply Chain BY Morgan Swink. PLEASE ONLY USE THIS BOOK AS YOUR GUIDE (CHAPTER 14)
Please review the transcript attached and use the insights from there to answer all these questions thoroughly. Also, please use the excel sheet to aid with answering (fill in all the information needed).
Collepals.com Plagiarism Free Papers
Are you looking for custom essay writing service or even dissertation writing services? Just request for our write my paper service, and we'll match you with the best essay writer in your subject! With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.
Get ZERO PLAGIARISM, HUMAN WRITTEN ESSAYS
Why Hire Collepals.com writers to do your paper?
Quality- We are experienced and have access to ample research materials.
We write plagiarism Free Content
Confidential- We never share or sell your personal information to third parties.
Support-Chat with us today! We are always waiting to answer all your questions.