Machine Utilization Gantt Chart -Sequence the jobs shown
Saudi Electronic University Machine Utilization Gantt Chart
Assignment Question(s): (Marks 5)
Question 1:
Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4.
Job Work Center/Machine Hours
Due Date (days) 1 A/3, B/2, C/2 3 2 C/2, A/4 2 3 B/6, A/1, C/3 4 4 C/4, A/1, B/2 3
a) Using finite capacity scheduling, draw a Gantt chart for the schedule (Marks 0.5)
b) What is the makespan? (Marks 0.5)
c) How much machine idle time is there? (Marks 0.5) d) How much idle time (waiting time) is there for each job? (Marks 0.5)
e) When is each job delivered? (Marks 0.5)
f) Which department is the bottleneck? (Marks 0.5)
g) Calculate the machine utilization? (Marks 0.5)
Question 2: A public accounting firm requires the following activities for an audit: Activity A B C D E F G Immediate Predecessor A B, C A B, C E, D Activity time 3 2 5 2 4 6 5
a) Draw a network for this project? (Marks 0.5)
b) Make a forward pass and a backward pass to determine ES, LS, EF, and LF? (Marks 0.5)
c) What are the critical path? (Marks 0.5)
Collepals.com Plagiarism Free Papers
Are you looking for custom essay writing service or even dissertation writing services? Just request for our write my paper service, and we'll match you with the best essay writer in your subject! With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.
Get ZERO PLAGIARISM, HUMAN WRITTEN ESSAYS
Why Hire Collepals.com writers to do your paper?
Quality- We are experienced and have access to ample research materials.
We write plagiarism Free Content
Confidential- We never share or sell your personal information to third parties.
Support-Chat with us today! We are always waiting to answer all your questions.