You have 24hrs to submit this for this components ? Final week, you are to finalize the overall project management plan (PMP) and to integrate all previously submitted components incorporat
You have 24hrs to submit this for this components
Final week, you are to finalize the overall project management plan (PMP) and to integrate all previously submitted components incorporated with instructor (project sponsor) feedback into a single project management plan. The project management plan will include the following components:
- Project quality management plan to include an updated scope, cost, schedule, communication, risk, resources, procurement, and quality)
- Project requirements – updated
- Stakeholder register – updated
- How project RAID (Risk, Assumption, Issues, and Dependencies)will be managed
- Project sponsor approval of the key project deliverables
Exactly 24hrs and attached files for ur reference of previous components
Project Charter
Aditya Panguluri
Trine University
11/3/2022
Project Title
Project Management for Mr. and Mrs. Rodgers Residential House Construction
Purpose
Mr. and Mrs. Rodgers and their family will develop a new primary dwelling through this construction project. It is expected to be finished in April, allowing the Rodgers family to move in within the first two weeks of May. Mr. Rodgers will relocate from Asia to North America to assume responsibility for his company's North American affairs in 2023. Therefore, the residence must be finished by April 30, 2023, so that the Rodgers can establish residency in the neighborhood with sufficient advance time for their children to register in the public education system along with their peers for the 2023 school year.
Description
This project is intended to construct a new home for Mr. and Mrs. Rodgers. The new home will be a high – end residential structure constructed on a three-acre lot – lot #38, situated at 101-819, Integer Road, Corona New Mexico, 02819, USA. The construction is scheduled to begin on Monday, November 6, 2022, and conclude on Sunday, April 30, 2023. This home is being created using the most up-to-date construction materials and specifications, as well as cutting-edge energy-saving technologies. Building will be supervised and managed by Top Home Solutions, the general contractor, who may outsource certain aspects of the operation. All labor will be insured, and all material will adhere to or exceed the requirements of the local code requirements.
Objective
According to the project description, the project must be completed by April 30, 2023. The following are the project's key achievement benchmarks:
1. Completed and certified architectural designs.
2. Construction permit approval.
3. Comprehensive lot preparation and clearance.
4. Foundation and footing excavation and establishment.
6. Waterproofing to all necessary surfaces..
7. Extensive driveway and landscaping.
8. Internal and external wiring installed.
9. HVAC completed.
10. Plumbing installations
11. Internal and external finishing achieved.
12. Comprehensive tour.
13. Awarded Certificate of Occupancy.
14. Approval of the interior and exterior checklist.
15. Completeness of interior and external punch list.
16. Complete approval review and key handover.
Success Criteria
1. All deliverables are met within expected timeframe.
2. Project team is satisfied with their role execution and the project result.
3. Project scope is met.
Funding
All funds has been pre-approved and deposited into a reserve account, from which the principal contract or agreement may draw. Starting with the second quarter following the commencement of work, the contractor may receive equal quarterly payments. The buyer will retain the first quarterly reimbursement until all work is finished and authorized at the project's conclusion and handover. Upon acceptable approval of the project's completion and transition, the buyer will make the final payment to the contractor.
Major Deliverables
According to the contractor's comprehensive floorplans and upgrade alternatives, all HVAC, landscape design, finish work, along with interior and exterior doors and cabinetry, and door and cabinetry components, sanitary fittings, household appliances, worktops, backsplash material, garage polishing work, floor coverings, and loft are Level V – Premium Grade. The buyer will pick plumbing fixtures, kitchen and laundry room fixtures, and appliances according to the schedule of details provided by the contractor. The contractor shall provide a provisional sum of $20,500 for lighting. All lighting needs exceeding the allocation will need submitting a modification order to the contractor.
Acceptance Criteria
1. Relevant milestones must be met within budgetary and schedule constraints.
2. To certify client satisfaction for each milestone.
3. Health and safety must be adhered to at each milestone.
4. Each milestone is completed in accordance with the technical, material, and quality specifications.
Milestone schedule
1. RFP and award
2. Design start
3. Target budget and scope
4. Guaranteed maximum price.
5. Construction starts
6. Project completion.
7. Defect liability period.
8. Handover.
Key Assumptions
1. During workweek, the project team will have access to the equipment, software, and electricity necessary to accomplish their particular responsibilities on time.
2. Personnel expenses will remain constant during the project's duration.
3. Additional material and resource expenses will stay constant throughout the duration of the project.
4. There will be no rise in the total cost of daily operations.
5. The project's scope will not alter over its life cycle.
Major Risks
1. Cost overruns.
2. Completion delays.
3. Environmental risks.
4. Design errors.
Approval requirements.
1. All materials acquired during the prior quarter will be shown on invoices.
2. Billing will reflect all work accomplished in the prior quarter.
3. Payment will be made quarterly in four (4) equal installments.
4. Any projected difference in material or labor costs that exceeds 2% in a single quarter or 5% overall requires the buyer's permission prior to purchase or performance.
5. All rising costs invoiced lacking prior permission as described in the preceding clause or by the purchaser will be paid at the contract document rate.
Project Manager
Role:
I. Project manager is responsible for the planning and execution of construction projects.
II. Guarantees that projects are executed on schedule and within budget constraints.
III. Organizes logistics, distribute tasks, and monitor expenditures.
IV. Coordinates schedules and activities with clients and construction specialists.
Sponsor Designee
Role:
1. Raises funds
2. Provides the description of work for the project
3. Gives data on the original project scope
4. Can stipulate project milestones, critical events, and the project's conclusion date
5. Determines the relative importance of the limitations
6. Offers information that aids in the development of the project's charter.
7. Provides the project manager with the power specified in the project charter
8. Assists in organizing work into suitable assignments
Approval signatures required:
_______________________ ____________________ __________________
Project manager, Signature Title Date
________________________ _____________________ ________________
Sponsor Designee, Signature Title Date
,
Surname5
Residential House Construction Project
Finalized Project Scope
This project is intended to construct a new home for Mr. and Mrs. Rodgers. This article offers data on the prospective resource allocation for the project, paying keen attention to the stakeholder and time assigned to the relevant milestones and tasks. From the information, a work schedule for the project is also given, The stakeholder engagement and communication plan is also given, offering information on the stakeholders involved in each phase of construction, the extent of their activities, and the timeframe within which their engagement is relevant. Finally, the work breakdown structure for the residential house project, highlighting the scope, milestones, and tasks involved in every phase of the project.
Stakeholder Engagement-Communication Plan
PHASE |
STAKEHOLDER |
ENGAGEMENT |
TIMEFRAME |
ACTIVITIES |
PRE-CONSTRUCTION |
Client, design team, specialists in relevant sectors, project manager, relevant authorities. Client, project manager, locals. |
Formal discussions conducted by the entity authorized to deliver the decisions that are consistent with statutory procedure during the environmental impact assessment and decision-making process. Acquiring a building permit as well as an occupancy permit. Getting permission to utilize the environment. Informal meetings and consultations with the locals. |
Reports on environmental assessments by end of January, 2023. Necessary permits by December, 2022. |
Publication of information on measures taken by the organization as part of the environmental impact assessment processes in the usual manner. Within the environmental protocol, there is a 21-day time for public consultations. Disclosure of information about project-related choices. Details about investing strategies. Information about processes for getting decisions. |
CONSTRUCTION |
Contractor and sub-contractors, client, construction workers, project manager. |
Unofficial engagements within the framework of the Stakeholder Involvement Plan. |
All throughout the construction process. |
Reminding them about contact details and the complaint reporting process. Establishment of regulations allowing construction workers to file comments. Details for the municipality and its residents. |
OPERATION |
Client, supervisors, project manager. |
Casual discussions within the framework of the Stakeholder Involvement Plan. |
Post-completion and assessment, and all through the operation process. |
Results are sent to responsible authorities in accordance with existing legislation, and relevant data is published on the construction company website. |
Resource Allocation
TASK |
ASSIGNED TO |
PROGRESS |
START |
END |
PRE-CONSTRUCTION |
|
|
|
|
Site preparation |
Client, Project manager |
100% |
12/8/22 |
12/11/22 |
Mobilization |
Project manager |
60% |
12/11/22 |
12/13/22 |
Site clearance |
Contractor |
100% |
12/13/22 |
12/17/22 |
Brief& design |
Design team, client |
100% |
12/17/22 |
12/26/22 |
Exca, and disposal |
Contractor |
100% |
12/12/22 |
12/18/22 |
CONSTRUCTION |
|
|
|
|
Concrete work |
Contractor, labor |
30% |
12/13/22 |
3/20/23 |
Woodwork-formwork |
Contractor, carpenters |
30% |
12/15/22 |
3/22/23 |
Metal work |
Contractor, blacksmiths |
0%
|
3/22/23 |
3/25/23 |
Joinery |
Contractor, suppliers |
0% |
3/22/23 |
3/24/23 |
Finishes |
Contractor, labor |
0% |
3/22/23 |
3/25/23 |
POST-CONSTRUCTION |
|
|
|
|
HVAC |
Contractor, specialists |
0% |
3/25/23 |
3/30/23 |
Electrical works |
Electrical engineer |
60% |
3/31/23 |
4/4/23 |
Mechanical installations |
Mechanical engineer |
75% |
4/5/23 |
4/10/23 |
Decorations |
Interior designer |
0% |
4/11/23 |
4/15/23 |
Landscaping |
Land surveyor |
20% |
4/5/23 |
4/9/23 |
PROJECT CONCLUSION |
|
|
|
|
Comprehensive tour |
Client, PM, contractor |
0% |
4/9/23 |
4/10/23 |
Certificate of occupancy |
Contractor, local authorities |
0% |
4/15/23 |
4/18/23 |
Approvals |
Local authorities |
10% |
4/15/23 |
4/18/23 |
Punch list |
Local authorities |
0% |
4/15/23 |
4/18/23 |
Handover |
Contractor, PM, client |
0% |
4/19/23 |
4/19/23 |
Work Schedule
WBS Structure
image5.png
image6.png
image7.png
image8.png
image9.png
image10.png
image11.png
image12.png
image13.png
image14.png
image15.png
image16.png
image17.png
image18.png
image19.png
image20.png
image21.png
image22.png
image23.png
image24.png
image25.png
image26.png
image27.png
image28.png
image29.png
image30.png
image31.png
image32.png
image33.png
image34.png
image35.png
image36.png
image37.png
image38.png
image39.png
image40.png
image41.png
image42.png
image43.png
image44.png
image45.png
image46.png
image47.png
image48.png
image49.png
image50.png
image51.png
image52.png
Collepals.com Plagiarism Free Papers
Are you looking for custom essay writing service or even dissertation writing services? Just request for our write my paper service, and we'll match you with the best essay writer in your subject! With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.
Get ZERO PLAGIARISM, HUMAN WRITTEN ESSAYS
Why Hire Collepals.com writers to do your paper?
Quality- We are experienced and have access to ample research materials.
We write plagiarism Free Content
Confidential- We never share or sell your personal information to third parties.
Support-Chat with us today! We are always waiting to answer all your questions.
image5.png
image6.png
image7.png
image8.png
image9.png
image10.png
image11.png
image12.png
image13.png
image14.png
image15.png
image16.png
image17.png
image18.png
image19.png
image20.png
image21.png
image22.png
image23.png
image24.png
image25.png
image26.png
image27.png
image28.png
image29.png
image30.png
image31.png
image32.png
image33.png
image34.png
image35.png
image36.png
image37.png
image38.png
image39.png
image40.png
image41.png
image42.png
image43.png
image44.png
image45.png
image46.png
image47.png
image48.png
image49.png
image50.png
image51.png
image52.png
Collepals.com Plagiarism Free Papers
Are you looking for custom essay writing service or even dissertation writing services? Just request for our write my paper service, and we'll match you with the best essay writer in your subject! With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.
Get ZERO PLAGIARISM, HUMAN WRITTEN ESSAYS
Why Hire Collepals.com writers to do your paper?
Quality- We are experienced and have access to ample research materials.
We write plagiarism Free Content
Confidential- We never share or sell your personal information to third parties.
Support-Chat with us today! We are always waiting to answer all your questions.