Consider the scenario and then develop a finalisation plan including procedures and activities that need to take place.
Consider the scenario and then develop a finalisation plan including procedures and activities that need to take place. (3,850 words)
The plan has been started for you. Not all aspects will apply to all projects.
A large state government department sought the design and establishment of:
an intranet facility within and across the department to enable internal communication and reporting
a secure online facility to enable communications with other departments
a portal to enable access to specified areas of department functions/ information
a reporting system that would enable costing to be calculated on a user pays basis for external users—this part of the system includes an extensive database of contracted organisations, including their funding arrangements with the department
The head of the department approached Aject International to provide a submission that would include a business case for development and implementation of such a system.
Profile of the client
The government department had a newly elected Minister who was required to sign off on the proposal and on the finished product and required periodic reporting. The Minister was under intense pressure at the time to reduce the budget deficit and to report increased efficiencies. This invariably brought resistance and opposition from those who were fearful of losing their jobs.
Project higher authorities
The department was divided into three main areas, with a senior executive at the head of each. The proposal had the strong support of two of the three executives. The third believed the work should be undertaken internally to protect the jobs of the existing staff in the information technology service area.
The sponsor
The sponsor for the project was a senior staff member from the section of the department managed by the dissenting senior executive.
Quality measures
Success of the project was dependent on winning over the support of departmental staff who wanted to see that it improved existing arrangements, as well as other end users of the system external to the department. They also needed to be consulted about the specifications for the new system.
Time frame
The project ran for 12 months and included the design, development and implementation of equipment and infrastructure, trialling and training of all users (no further training was to be delivered once the project was completed). The time frame was very tight and a key issue was seeking and incorporating feedback from end users at a time at which they were unfamiliar with the product.
Project scope
Since no one internally seemed to have the capacity to understand or scope the requirements for the system, specifications were left fairly open, relying on Aject to provide what they believed to be the best-fit solution to the problem: to increase efficiency across the organisation.
Project communications
Managing project communications across the team was carefully considered since the team members were located in different states and each one had substantial existing business commitments. Throughout the project, team members struggled with implementing the communication processes agreed in the original communications plan. Despite this the project was able to come in on time but did require some minor modifications to the scope of the final product to accommodate changes in technology between the beginning and end of the project.
The project team
Aject International agreed to pull together a consortium that included three other companies as subcontractors: AJC, SPS (Software Performance Systems) and Orbit.
Aject provided the project manager and three of its 20 staff assisted in project administration.
AJC specialised in designing system architecture and troubleshooting. They had just picked up several large contracts in Asia and were experiencing a substantial demand on their resources so they needed to recruit additional staff to provide the technical expertise to the project.
SPS was a small but vibrant company that undertook all the communication and consultation activities with stakeholders and the end users of the system throughout the project and provided training to them in the latter stages of the project.
Orbit specialised in data management systems and designed, installed and piloted software modifications (they used off the shelf software). They were also responsible for procuring all required hardware and software.
Finalisation plan area: Include?; Details of procedure or activity (eg how);
Transition of responsibility or ownership of the project to the client or customer
Transfer of assets to the customer, or back to the original owner
Collepals.com Plagiarism Free Papers
Are you looking for custom essay writing service or even dissertation writing services? Just request for our write my paper service, and we'll match you with the best essay writer in your subject! With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.
Get ZERO PLAGIARISM, HUMAN WRITTEN ESSAYS
Why Hire Collepals.com writers to do your paper?
Quality- We are experienced and have access to ample research materials.
We write plagiarism Free Content
Confidential- We never share or sell your personal information to third parties.
Support-Chat with us today! We are always waiting to answer all your questions.