A final report which describes and documents your analysis and design efforts of the proposed solution. Your report must include at a minimum A brief description of the
A final report which describes and documents your analysis and design efforts of the proposed solution. Your report must include at a minimum
- A brief description of the problem, functionality of your proposed information system solution, and the business benefits gained by implementing it.
- Artifacts such as use case diagrams, activity diagrams, context level data flow diagrams, E-R diagrams, user interfaces etc. used in your information needs/requirements specification and the systems design.
- List of the hardware and software required to meet the needs of your business problem.
- A brief discussion on what kind of a project methodology do you envision to use to implement your proposed solution. Include in your discussion the possible project scope and risk issues, you may encounter.
Note: For 1st and 2nd bullet points, you can use your assignment work and add it to the report
Book.xlsx
Sheet1
Project Planner | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Select a period to highlight at right. A legend describing the charting follows. | Period Highlight: | 1 | Plan Duration | Actual Start | % Complete | Actual (beyond plan) | % Complete (beyond plan) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
ACTIVITY | PLAN START | PLAN DURATION | ACTUAL START | ACTUAL DURATION | PERCENT COMPLETE | PERIODS | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 | 50 | 51 | 52 | 53 | 54 | 55 | 56 | 57 | 58 | 59 | 60 | 61 | 62 | 63 | 64 | 65 | 66 | 67 | 68 | 69 | 70 | 71 | 72 | 73 | 74 | 75 | 76 | 77 | 78 | 79 | 80 | 81 | 82 | 83 | 84 | 85 | 86 | 87 | 88 | 89 | 90 | 91 | 92 | 93 | 94 | 95 | 96 | 97 | 98 | 99 | ## | ## | ## | ## | ## | ## | ## | ## | ## | ||||||
Sprint 1 Initiation (Oct 14 – Oct 28) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Create Project Vision | 1 | 15 | 1 | 7 | 100% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Identify Scrum master and stakeholder | 1 | 15 | 1 | 7 | 100% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Form Scrum Team | 1 | 15 | 7 | 5 | 100% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Obtain Necessary Developmental and Managerial Approvals | 1 | 15 | 7 | 6 | 75% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Create Product Backlog | 1 | 15 | 9 | 7 | 50% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Sprint 2 Planning and Preparing (Oct 29 – Nov12) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Create deliverables | 16 | 15 | 16 | 15 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Choose overall software layout | 16 | 15 | 16 | 7 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Choose all the analytic tools to be implemented | 16 | 15 | 16 | 7 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Estimate tasks | 16 | 15 | 16 | 7 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Create user stories and tasks | 16 | 15 | 23 | 8 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Create sprint backlog | 16 | 15 | 23 | 8 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Sprint 3 Implementation (Nov 14 – Nov 28) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Create deliverables | 31 | 15 | 31 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Create tasks for newly raised issues | 31 | 15 | 31 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Conduct daily standup | 31 | 15 | 31 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Groom prioritized product backlog | 31 | 15 | 31 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Sprint 4 Implementation (Nove 29 – Dec 13) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Create deliverables | 46 | 15 | 46 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Create tasks for newly raised issues | 46 | 15 | 46 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Conduct daily standup | 46 | 15 | 46 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Groom prioritized product backlog | 46 | 15 | 46 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Sprint 5 Implementation (Dec 14 – Dec 28) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Create deliverables | 61 | 15 | 61 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Create tasks for newly raised issues | 61 | 15 | 61 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Conduct daily standup | 61 | 15 | 61 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Groom prioritized product backlog | 61 | 15 | 61 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Sprint 6 Review and Retrospect (Dec 29 – Jan 12) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Create and conducts necessary tests for de development team | 76 | 15 | 76 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Demonstrate and validate software | 76 | 15 | 76 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Request and evaluate team’s feedback on project execution | 76 | 15 | 76 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Provide accessed to the Dashboard to data analytics for review | 76 | 15 | 76 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Create and conducts necessary tests for de development team | 76 | 15 | 76 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Demonstrate and validate software | 76 | 15 | 76 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Request and evaluate team’s feedback on project execution | 76 | 15 | 76 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Sprint 7 Release (Jan 13 – Jan 27) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Ship Deliverables | 91 | 15 | 91 | 1 | 0% | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Retrospect Project | 91 | 15 | 91 | 1 | 0% |
Project Planning Phase.docx
Swift trade corp project plan
June 26, 2022
Baseline Project Plan
Scope Statement:
Project objective –
Develop a business intelligence dashboard to be used by the Analytics and Marketing departments to conveniently analyze data and present key insights in an easy-to-use and intuitive manner.
Justification for the project –
This project attempts to solve operational problems encountered by data analytics professionals at Swift Trade Corp. The business intelligence dashboard will facilitate the process of presenting data and other important business metrics important to the company’s performance.
Execution approach –
The Scrum framework will be utilized for this project. A team of nine collaborating individuals with targeted expertise will be organized and tasks will be shared among them. A Project Manager will lead this team to ensure efficient and timely deliveries.
The structure of the team will be as follows:
· 2 Software Developers
· 2 Full Stack Developers
· 2 Business Analysts
· 1 Statistician
· 2 UX Designer
· 1 Project Manager
Timeline –
Based on the specification of the job and other related past deliveries, this is predicted to be a short-term project, set to range between 3-4 months.
The project will begin on October 24, 2022. The time of completion for each consecutive sprint will be 2 weeks. Assuming no major implications were encountered, the release of the finished software to a production environment is scheduled to take place on January 16, 2023.
Timeline/Sprint |
Working Phase: |
Objectives |
1st Sprint (Oct 14 – Oct 28) |
Initiation |
· Create project vision · Identify Scrum Master and stakeholder · Form Scrum team · Obtain Necessary Developmental and Managerial Approvals · Create Product Backlog |
2nd Sprint (Oct 29 – Nov 12) |
Planning and Preparing |
· Create deliverables · Choose overall software layout · Choose all the analytic tools to be implemented · Create user stories and tasks · Estimate tasks · Create sprint backlog |
3rd Sprint (Nov 14 – Nov 28 4th Sprint (Nov 29 – Dec 13) 5th Sprint (Dec 14 – Dec 28) |
Implementation |
· Create deliverables · Create tasks for newly raised issues · Conduct daily standup · Groom prioritized product backlog |
6th Sprint (Dec 29 – Jan 12) |
Review and Retrospect |
· Create and conduct necessary tests for the development team · Demonstrate and validate software · Request and evaluate team’s feedback on project execution · Provide access to the Dashboard to data analytics for review · Create and conduct necessary tests for the development team · Demonstrate and validate software · Request and evaluate team’s feedback on project execution |
7th Sprint (Jan 13 – Jan 27) |
Release |
· Ship Deliverables · Retrospect Project |
Proposed System
Name of Software Offer: DashViz – A Business intelligence Dashboard with sophisticated tools for data exploration.
System development recommendation-
After an exhaustive investigation heavily focused on the business’ demands, the Information Systems team has provided its definite professional opinion. Developing the Business Intelligence Dashboard from the ground up, using a secure web-based approach appears to be the most suitable method.
This method of implementation provides the highest level of customization, which will be fitted to our business needs and allows for ease of access for both internal and external users to the application without the need to download any software.
Utilization Purposes-
The development of this dashboard will be heavily focused on the manipulation of data and visual, dynamic representation of the data types most used by Swift Trade Corp.
· Product data- Data displaying products features, important for supply chain, inventories, and pricing.
· Customer information data – This provides details about the customers buying from our website and their purchases.
· Sales data- Includes all the transactions for the current day and historic accountings. Used to optimize prices, predict demand, and develop a marketing plan.
Benefits of the Software-
· The Business intelligence dashboard will aid professionals to quickly gain insights into the most important aspects of their data
· Dashboards are vital for better decision making
· The Administration department, Managers and Stakeholders will benefit by reviewing the bigger picture of operations.
· The Marketing department will gain deeper insights into the market's movement and take business decisions accordingly.
· managers to review the bigger picture of business operations
· Provides the ability to view real time financial results such as revenue and expenses.
Other Alternatives-
The team has weighed the alternatives, some of which include using existing out-of-the-box software which can be costly and lacks customizability, in some cases the risk of exposure of sensitive business data has been an important deciding factor. The alternative yielding the highest software efficiency and performance is the app-based approach, but there are known issues to this; Accessibility computers using different operating systems can be complex, employees report to use primarily use Windows as their operating System, but a significant number utilize MacOS and Linux which both have an Arm-based architecture compared to the x-64 x-86.
A backwards combability extension can be arranged, though it would drastically prolong the timeline for this project and compromises performance.
Feasibility Assessment
Ideas
A. cost estimates -> budget allocation and estimated expenditures will be included in a cost estimate table’
B. Intangible benefits
C. Technical
The only technical risk the company faces with the creation of the new dashboard is a security issue or bugs. There will be ongoing maintenance for the software which is to be included in the cost analysis.
D. Operational
All staff will be trained on the new dashboard to recognize their key performance indicators and management will coach everyone who is lacking in KPIs.
E. Inclusions/Exclusions
Marketing will gain insight into key performance indicators
Management Issues
Ideas
Team selection
Processing functions
Organizational
Constraints
Goals
Deadlines
Expectations/Assumptions
Mia, Paul and John are all of the software developers who will be creating the dashboard.
John will deal with the entire testing processes and will write and perform the test plans
Communications:
Successful communication will be ensured through communication management plans
Weekly Status reports of the project update will be generated for all stakeholders and upper management.
Exclusions from scope
Fake information about the corporation **Todelete
Name: Swift Trade Corp
About the company: E-Commerce company that focuses on selling a variety of products (ex. Amazon, Ebay)
Project begins: January 16, 2023.
Ends: Jan 13 – Jan 27)
Swift Trading Corp.
Project Charter
Prepared: June 26, 2022
Project Name: Project Plan
Project Manager: Jorge Alvarez
Customer: Analysis/Marketing
Project Sponsor: Erik Helms
Project Start/End (projected): 10/24/2022 – 1/16/2023
Project Overview:
This project will implement a business intelligence dashboard to allow the analytics and marketing departments to conveniently and efficiently analyze data and present key insights that will save the company time and effectively relay information.
Objectives:
· Solve operational problems
· Facilitate the data presentation process
· Facilitate other business metrics related to company performance
Key Assumptions:
· System will be built in house
· Interface will be a web browser
· Achieving the highest level of customization
· Allow access to internal and external users
· System will negate the need to download software
Stakeholders and Responsibilities:
Stakeholder |
Role |
Responsibility |
Signatures |
Jorge Narvaez |
Project Manager |
Planning, Monitoring, Execution |
Jorge Narvaez |
Erik Helms |
Marketing Director |
Monitoring, Resources |
Erik Helms |
Jonathan Giles |
CIO (Chief Investment Office) |
Monitoring, Resources |
Jonathan Giles |
Erica Winstead |
Analytics Director |
System functionality, Resources |
Erica Winstead |
,
design_Mockup1.pdf
Untitled
July 25 2022
Contents
1. Page 1
ERDiagramDashboardApp.pdf
RegisteredUsersRegisteredUsers UserLogInCredentialsUserLogInCredentials
ApiEntryPointApiEntryPoint
PermissionsPermissions
RolesRoles
DashboardAppDashboardApp
ThirdPartyApisTokensThirdPartyApisTokens
EnterpriseFilesystemEnterpriseFilesystem
empIDempID intPK intPK
nameFirstnameFirst nvarch ar(15)
nvarch ar(15)
nameLastnameLast nvarch ar(15)
nvarch ar(15)
empIDUs ernameempIDUs ername nvarch ar(20)
PK nvarch ar(20)
PK
empIDempID intFK intFK
usernameusername char(1
0) char(1
0)
apiR equestUsernameapiR equestUsername nvarch ar(10)
PK nvarch ar(10)
PK
userRoleIDuserRoleID intint
authTokenauthToken intint
empIDUs ernameempIDUs ername nvarch ar(15)FK
PK nvarch ar(15)FK
PK
authorizationsauthorizations intint
rights ProfilesGranted rangerights ProfilesGranted range intint
userRoleIDuserRoleID int FK
PK int
FK
PK
roleNameroleName varcha
r(15) varcha
r(15)
createdAtcreatedAt dateti
me dateti
me
empIDUs ernameempIDUs ername int FK
PK int
FK
PK
thi rdPartyProductsthi rdPartyProducts nvarch ar(200
)
nvarch ar(200
)
analysisToolsCus tomanalysisToolsCus tom intint
requestTokenrequestToken nvarch ar(200
) PK
nvarch ar(200
) PK
googleanalyticsgoogleanalytics nvarch ar(200
)
nvarch ar(200
)
sqlPostGressqlPostGres nvarch ar(200
)
nvarch ar(200
)
empIDUs ernameempIDUs ername intPK intPK
hardDrivehardDrive intint
documentsdocuments intint
emailemail nvarch ar(15)
nvarch ar(15)
isContractor defaultisContractor default bit bit
employedDateemployedDate dateti
me dateti
me
pas swordpas sword nvarch ar(10)
nvarch ar(10)
accountType domainaccountType domain char(3
) char(3
)
userRoleIDuserRoleID intFK intFK
updatedAtupdatedAt dateti
me dateti
me
das hboardAppAuthdas hboardAppAuth intint
apiR equestUsernameapiR equestUsername intFK intFK
templates Customtemplates Custom intint
apiR equestUsernameapiR equestUsername nvarch ar(200
) FK
nvarch ar(200
) FK
requestTokenrequestToken nvarca hr(200
) FK
nvarca hr(200
) FK
sqlLitesqlLite nvarch ar(200
)
nvarch ar(200
)
OracleOracle nvarch ar(200
)
nvarch ar(200
)
caliRalicaliRali nvarch ar(200
)
nvarch ar(200
)
keyMetrickeyMetric nvarch ar(200
)
nvarch ar(200
)
mySqlmySql nvarch ar(200
)
nvarch ar(200
)
sharedDocumentssharedDocuments intint
- 5452a416-8a8d-4e87-9328-a36f2ea69c37.vsdx
- Page-1
Collepals.com Plagiarism Free Papers
Are you looking for custom essay writing service or even dissertation writing services? Just request for our write my paper service, and we'll match you with the best essay writer in your subject! With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.
Get ZERO PLAGIARISM, HUMAN WRITTEN ESSAYS
Why Hire Collepals.com writers to do your paper?
Quality- We are experienced and have access to ample research materials.
We write plagiarism Free Content
Confidential- We never share or sell your personal information to third parties.
Support-Chat with us today! We are always waiting to answer all your questions.