You will create a Quality Management plan that identifies quality standards for the Garage Apartment case. Using the WBS created in the prior assignment, identify all th
You will create a Quality Management plan that identifies quality standards for the Garage Apartment case. Using the WBS created in the prior assignment, identify all the deliverables and create quality assurance and quality control processes to ensure the Garage Apartment will be constructed with quality. The quality processes and measurements should focus on project quality as well as product .
Please fill the content for attachment Quality Management Plan.
Also attached case and Gannt Chart for reference pupose.
Garage Apartment Project
1
Introduction
The following project is to build a garage apartment building (new stand-alone building) on existing land. This project is to be the basis for assignments in IT401. The project is described below. This project will follow a standard home construction project WBS similar to the one shown below. This WBS is meant to be a template, not the specific WBS for the project which will be one of your assignments.
Garage Apartment Project
Assumptions
1. Assume that you already have the property and it is paid for so do not include the cost of the real estate in your calculations.
2. Assume that utilities such as water, sewage, and electric are available to the property. You will only need to schedule the connections to theses utilities.
3. Assume that all applicable building codes and regulations will be followed for permits and inspections.
4. Assume that you have a complete set of blueprints and an approved building permit. All you need to do is schedule the actual construction. (Hint: the start milestone could be “Building permit received.”).
Scope Statement
Build a 2- car garage with an apartment/office on the second floor on your existing building lot in accordance with applicable building codes. The start date is 01 Feb 18 and a planned finish date of 30 Jun 10. The budget for construction is $160,000.
Project design and floor plan
Elevation View
First Floor
Second Floor
,
Quality Management Plan
Garage Apartment Project
PQR Construction
123 Purdue
Internet, IN 23456
July 5th, 2022
1
8
Table of Contents
Quality Requirements / Standards 3
Quality Control Measurements 6
Introduction
A quality management document is a vital document that outlines how construction quality objectives are met. The quality assurance team utilizes this test strategy to guide them in the in-testing process (Guo, 2021). The test strategy should be shared with all members of the quality assurance team to ensure they are on the same page regarding their responsibilities and the approach to be followed. Test strategy starts as a thought process that helps in discovering missing requirements, defining the scope of the testing (Zhou, 2018). For the project managers, test strategy enables them to get a vivid picture of the project status at any time. The goal of this paper is to demonstrate case scenarios of testing garage apartment project. The test strategy document will outline the actual quality check technique to be used and how the feedback is collected from both client and subcontractors.
Quality Management Approach
A Quality Plan prepared and submitted by the project manager and contractors defines the methods and metrics that will used to monitor, measure, document, report and deliver the work conforming to and in compliance with the original specifications. The plan will include the contractor’s personnel or third party responsible for managing, inspection and executing the plan and will provide the means and methods to communicate, document, mitigate and correct those items that fail to meet the terms of the contract.
The quality management approach for the LTFC project will ensure quality is planned for both the product and processes. In order to be successful, this project will meet its quality objectives by utilizing an integrated quality approach to define quality standards, measure qualityquality, and continuously improve quality.
Product quality for the LTFC project will be defined by the company’s current standards and criteria for its fiber optic cable family. The focus is on the project’s deliverable and the standards and criteria being used will ensure the product meets established quality standards and customer satisfaction.
Process quality for the LTFC project will focus on the processes by which the project deliverable will be manufactured. Establishing process quality standards will ensure that all activities conform to an organizational standard which results in the successful delivery of the product.
The project team will work with the Quality Group to define and document all organizational and project specific quality standards for both product and processes. All quality documentation will become part of the LTFC Project Plan and will be transitioned to operations upon the successful completion of the project.
Metrics will be established and used to measure quality throughout the project life cycle for the product and processes. The Quality Group Manager will be responsible for working with the project team to define these metrics, conduct measurements, and analyze results. These product and process measurements will be used as one criterion in determining the success of the project and must be reviewed by the project sponsor. Metrics will include:
· Schedule
· Resources
· Cost
· Process performance
· Manufacturing line utilization
· Material waste
· Product performance
· Attenuation
· Tensile strength
· Customer Satisfaction (as a result of field trials)
Quality improvements will be identified by any member of the project team or quality group. Each recommendation will be reviewed to determine the cost versus benefit of implementing the improvement and how the improvement will impact the product or processes. If an improvement is implemented the project manager will update all project documentation to include the improvement and the quality manager will update the organizational documentation the improvement affects.
Quality Requirements / Standards
This section should describe how the project team and/or quality group will identify and document the quality requirements and standards. Additionally, there should also be an explanation of how the project will demonstrate compliance with those identified quality standards. The quality standards and requirements should include both the product and processes.
Product Quality:
The product quality standards and requirements will be determined by the project team and quality group. These standards will primarily be based on the company’s documented standards for all fiber optic cables. There may be product-specific quality standards identified that are not currently part of the documented organizational standards. In this case, the quality group will review these newly identified standards and incorporate them into organizational documentation if approved. The project team will also document any newly identified quality standards into the LTFC project plan and ensure communication with all stakeholders.
As trial products are measured at pre-determined intervals, we will know that the product is compliant with quality standards once we achieve ten consecutive trial runs resulting of cable which is 100% within acceptable quality control margins.
Process Quality:
The process quality standards and requirements will be determined by the project team and quality group. Many of these standards will be based on existing company process standards. However, it is anticipated that there will be several unique steps in the manufacturing of the LTFC product which will require new quality standards. The LTFC project team will work with the quality group to establish acceptable standards and document these standards for incorporation into both organizational process documents as well as the LTFC project plan. These standards will be communicated to all project stakeholders.
As trial products are created, the process metrics will be measured and analyzed to determine the quality of the process. Once the LTFC product meets quality compliance and all process metrics fall within acceptable quality assurance margins, we will achieve process compliance for the LTFC project.
Quality Assurance
This section should explain how you will define and document the process for auditing the quality requirements and results from quality control measurements in order to ensure that quality standards and operational definitions are used. This section should also document the actual quality assurance metrics used for this project.
The quality assurance of the LTFC Project focuses on the processes used in the manufacturing of the LTFC product. In order to ensure quality, an iterative quality process will be used throughout the project life cycle. This iterative process includes measuring process metrics, analyzing process data, and continuously improving the processes.
The LTFC Project Manager and the project team will perform assessments at planned intervals throughout the project to ensure all processes are being correctly implemented and executed. Key performance metrics for the manufacturing of the LTFC product include polyethylene (PE) waste, fiber waste, and time per cable run for each phase of cable creation (buffering, stranding, and jacketing). The established project tolerances for these metrics are the organizational standards for all other cable products. The table below provides the key quality assurance metrics for the LTFC Project.
Process Action |
Acceptable Process Standards |
Process Phase |
Assessment Interval |
Fiber Tube Buffering |
· < 20 feet fiber waste per tube · < 0.5 lbs PR waste per tube · < 8 minutes per linear km of buffer tube |
Buffering |
Daily or per run |
Fiber Tube Stranding |
· < 10 feet of waste per stranded core · < 12 minutes per linear km of stranded core |
Stranding |
Daily or per run |
Core Jacketing |
· < 15 feet of waste per jacketed cable · < 3 lbs PE waste per cable · < 12 minutes per linear km of jacketed cable |
Jacketing |
Daily or per run |
The quality manager will provide day to day quality management and conduct process audits on a weekly basis, monitor process performance metrics, and assure all processes comply with project and organizational standards. If discrepancies are found, the quality manager will meet with the Project Manager and review the identified discrepancies.
The Project Manager will schedule regularly occurring project, management, and document reviews. In these reviews, an agenda item will include a review of project processes, any discrepancies and/or audit findings from the quality manager, and a discussion on process improvement initiatives.
Process improvement is another aspect of quality assurance. Quality assurance reviews, findings, and assessments should always result in some form of process improvement and, as a result, product improvement. All process improvement efforts must be documented, implemented, and communicated to all stakeholders as changes are made.
Quality Control
This section describes how you will define and document the process for monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes. Quality control applies to the project’s product as opposed to its processes. It should include what the acceptable standards and/or performance are for the product and how these measurements will be conducted.
The quality control of the LTFC project focuses primarily on the LTFC product and the acceptable standards and performance. The quality performance standards for the LTFC Project are in accordance with the organizational standards of performance of all fiber optic cable products. However, there are several project-specific quality standards which were established specifically for the LTFC Product. All trial cables which are produced will be submitted to the characterization group for standard loose tube cable performance testing. Additionally, all physical measurements will conducted on each produced cable to ensure compliance with established quality standards. The table below illustrates all performance and physical quality standards for the LTFC Product:
Product |
Physical/Performance Standards |
Quality Assessment Activities |
Assessment Intervals |
6-36 fiber loose tube cable |
0.75” +/- 0.01” diameter > 300 N/m2 Tensile Strength < 5% attenuation at 625nm wavelength |
Lab and field testing |
Per produced cable length |
42-188 fiber loose tube cable |
1.5” +/- 0.01” diameter > 450 N/m2 Tensile strength < 5% attenuation at 625nm wavelength |
Lab and field testing |
Per produced cable length |
194-288 fiber loose tube cable |
2.25” +/- 0.001” diameter > 600 N/m2 Tensile strength < 5% attenuation at 625nm wavelength |
Lab and field testing |
Per produced cable length |
The project team will perform all physical measurements on their trial cables. The characterization group will perform attenuation testing and will provide the results back to the project team within 3 business days after the test sample is submitted. The quality group will ensure all physical and performance standards are met for each trial cable, perform audits, and assist the project team with creating or updating all documentation related to product quality.
The Project Manager will schedule regularly occurring project, management, and document reviews. In these reviews, an agenda item will include a review of products, any discrepancies and/or audit findings from the quality manager, and a discussion on product improvement initiatives.
It is imperative to the success of the project that all of the established physical and performance standards are met. By doing so, the LTFC Project Team will ensure that the product achieves the high level of customer satisfaction anticipated and that future operational cable production will be in line with budget and resource allocations.
Quality Control Measurements
This section should contain a sample or useable table/log to be used in taking quality measurements and comparing them against standards/requirements. These forms may be found in many different styles or formats. The most important aspect of this log is to provide documentation of the findings. If actual measurements do not meet the standards or requirements then some action must be taken. This may be done in regularly scheduled project status meetings or as necessary throughout the project lifecycle.
All LTFC Project products and processes must be measured and fall within the established standards and tolerances. The below logs will be used by the project and quality teams in conducting these measurements and will be maintained for use as supporting documentation for the project’s acceptance.
Quality Assurance Log
Trial # |
Date |
Process Measured |
Required Value |
Actual Measured |
Acceptable? (Y/N) |
Recommendation |
Date Resolved |
Quality Control Log
Cable # |
Date |
Item Measured |
Required Value |
Actual Measured |
Acceptable? (Y/N) |
Recommendation |
Date Resolved |
Sponsor Acceptance
Approved by the Project Sponsor:
Date:
<Project Sponsor>
<Project Sponsor Title>
This free Project Quality Management Plan Template is brought to you by www.ProjectManagementDocs.com
,
GanttChart
Garage apartment Project Schedule | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Innovation Rennovation | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Project Start Date | 44683.0 | Display Week | 1 | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 | Week 8 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
Project Lead | 2 May 2022 | 9 May 2022 | 16 May 2022 | 23 May 2022 | 30 May 2022 | 6 Jun 2022 | 13 Jun 2022 | 20 Jun 2022 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | ||||||||||
WBS Vertex42: Work Breakdown Structure Level 1: 1, 2, 3, … Level 2: 1.1, 1.2, 1.3, … Level 3: 1.1.1, 1.1.2, 1.1.3, … – The WBS uses a formula to control the numbering, but the formulas are different for different levels. Copy and Paste the cells in the WBS column from the examples at the bottom of the worksheet. |
TASK Vertex42: Task Description Enter the name of each task and sub-task. Use indents for sub-tasks. |
LEAD Vertex42: Task Lead Enter the name of the Task Lead in this column. |
PREDECESSOR Vertex42: Predecessor Tasks: You can use this column to enter the WBS of a predecessor for reference. The PRO version uses formulas to automatically calculate the Start Date based on the Predecessor. |
START Vertex42: Task Start Date You can manually enter the Start Date for each task or use a formula to create a dependency on a Predecessor. For example, you could enter =enddate+1 to set the Start date to the next calendar day, or =WORKDAY(enddate,1) to set the Start date to the next work day (excluding weekends), where enddate is the cell reference for the End date of the Predecessor task. |
END Vertex42.com Templates: End Date: The End Date is calculated based on the Start Date and the Calendar Days columns. |
DAYS Vertex42: Duration (Calendar Days) The duration is the number of calendar days for the given task. The duration is calculated as the End Date minus the Start Date plus 1 day, so that a task starting and ending on the same day has a duration of 1 day. Note: The conditional formatting used to create the gantt chart references this column. |
% DONE Vertex42: Percent Complete Update the status of this task by entering the percent complete (between 0% and 100%). |
WORK DAYS Vertex42: Work Days Counts the number of work days, excluding the weekends (Saturday and Sunday). In the PRO version, you can customize the work week and list specific non-working days like holidays. In the PRO version, the default input is the Work Days instead of the Calendar Days. |
M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | |
1 | Project Planning | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1.1 | Planning | Project manager | Mon 5/02/22 | Fri 5/06/22 | 5 | 100% | 5 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1.2 | Understanding the client requirement. | Sat 5/07/22 | Wed 5/11/22 | 5 | 100% | 3 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1.3 | Estimate budget. | Planner | Thu 5/12/22 | Sun 5/15/22 | 4 | 100% | 2 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1.4 | Plans and drawing. | Architect | Mon 5/16/22 | Thu 5/19/22 | 4 | 100% | 4 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1.5 | Create plot with measurement. | Architect | Fri 5/20/22 | Tue 5/24/22 | 5 | 100% | 3 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1.6 | Create project schedule. | Project Manger | Wed 5/25/22 | Tue 5/31/22 | 7 | 100% | 5 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 | Structure | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2.1 | Grading and drain. | Wed 6/01/22 | Sat 6/04/22 | 4 | 100% | 3 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2.2 | Procuring concrete, Iron, and gravel. | Tue 6/05/18 | Tue 6/05/18 | 1 | 100% | 1 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2.3 | Foundation. | Mon 6/06/22 | Wed 6/08/22 | 3 | 100% | 3 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2.4 | Footings. | Thu 6/09/22 | Tue 6/14/22 | 6 | 80% | 4 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3 | Framing | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3.1 | Framing material estimation | Wed 6/15/22 | Wed 6/15/22 | 1 | 0% | 1 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3.2 | Order framing materials and set delivery date. | Thu 6/16/22 | Thu 6/16/22 | 1 | 0% | 1 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3.3 | Frame, beams, ties, and trusses. | Fri 6/17/22 | Sun 6/19/22 | 3 | 0% | 1 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3.4 | Frame exterior walls. | Mon 6/20/22 | Sat 6/25/22 | 6 | 0% | 5 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3.5 | Frame windows. | </td
Collepals.com Plagiarism Free Papers Are you looking for custom essay writing service or even dissertation writing services? Just request for our write my paper service, and we'll match you with the best essay writer in your subject! With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers. Get ZERO PLAGIARISM, HUMAN WRITTEN ESSAYS Why Hire Collepals.com writers to do your paper? Quality- We are experienced and have access to ample research materials. We write plagiarism Free Content Confidential- We never share or sell your personal information to third parties. Support-Chat with us today! We are always waiting to answer all your questions. All Rights Reserved Terms and Conditions |