As a project management professional, it is important for you to be able to review numbers and report on what they are saying. It
As a project management professional, it is important for you to be able to review numbers and report on what they are saying. It is also important for you to be able to use software that helps you keep timelines and keep the project running on time and smoothly. This assignment will continue to help prepare you for your responsibilities.
You are a project manager and you successfully completed the project from Weeks 2 and 3. A program manager from another division is aware of your familiarity and success with the Technology Refresh Project. He has asked you to perform a schedule risk analysis on a different Technology Refresh Project, i.e., the Technology Refresh (Version B) Project, which is based on your project from Weeks 2 and 3. In fact, the project tasks are the same, only the durations and the critical paths are different (note: your project files from Week 2 and Week 3 are not relevant to this assignment).
Perform a schedule risk analysis for the Technology Refresh (Version B) Project by completing the following:
Open "Topic 4 Project Assessment Problems TEMPLATE." Take note of the project information, including the expected durations and the tasks that are on the critical path.
Calculate the following;
- The expected project finish time.
- The variances for the applicable tasks.
- The total critical path variance.
- The total critical path standard deviation.
The customer has seen the Technology Refresh (Version B) project schedule and the expected project finish time. However, the customer is concerned about the schedule risk of the project. Therefore, he wishes to know the following (i.e., determine the following):
- The probability of finishing the project in 287 days.
- The probability of finishing the project in 273 days.
Hints:
- If you wish to solve part 3 using the Z-value approach, refer to the Standard Normal Cumulative Probability Table at math.bgu.ac, (2014).
- Note also that Microsoft Excel's NORM.DIST function can be used to determine the probabilities in part 3, which does require use of the Z-Table.
Project Risk
MGT 640 Topic 4, Project Risk Assessment Problems SOLUTION | ||||||||
ID | Task | Optimistic Duration (days) | Most Likely Duration (days) | Pessimistic Duration (days) | PERT Expected Duration (days) | Critical Path | Variance | |
1 | TECHNOLOGY REFRESH (VERSION B) PROJECT | |||||||
2 | Initiating | |||||||
3 | Meet with key stakeholders | 2 | 3 | 12 | 4 | √ | ||
4 | Finalize statement of work | 2 | 10 | 15 | 10 | √ | ||
5 | Secure project team leads | 2 | 2 | 4 | 2 | |||
6 | Finalize stakeholder register | 2 | 10 | 13 | 9 | √ | ||
7 | Develop project charter | 2 | 5 | 17 | 7 | |||
8 | Finalize project charter | 2 | 4 | 8 | 4 | √ | ||
9 | Planning | |||||||
10 | Scope Planning | |||||||
11 | Requirements | |||||||
12 | Develop/finalize functional requirements | 10 | 18 | 28 | 18 | √ | ||
13 | Develop/finalize hardware requirements | 12 | 16 | 18 | 16 | |||
14 | Develop/finalize software requirements | 10 | 16 | 30 | 17 | |||
15 | Develop/finalize requirements traceability matrix | 11 | 14 | 28 | 16 | |||
16 | Finalize project deliverables | 2 | 2 | 3 | 2 | √ | ||
17 | Develop scope statement | 4 | 9 | 10 | 8 | √ | ||
18 | Finalize/Update WBS | 2 | 3 | 5 | 3 | √ | ||
19 | Schedule (Time) and Cost Planning | |||||||
20 | Finalize hardware/software costs | 2 | 4 | 5 | 4 | |||
21 | Update activities and duration estimates | 6 | 12 | 14 | 11 | √ | ||
22 | Human Resource Planning | |||||||
23 | Finalize resource requirements | 6 | 10 | 14 | 10 | |||
24 | Finalize project costs | 4 | 11 | 19 | 11 | |||
25 | Identify training requirements | 2 | 4 | 5 | 4 | √ | ||
26 | Complete training activities | 6 | 12 | 14 | 11 | √ | ||
27 | Quality Planning | |||||||
28 | Determine impacted quality processes | 2 | 3 | 4 | 3 | √ | ||
29 | Finalize quality management plan | 2 | 10 | 18 | 10 | |||
30 | Risk Planning | |||||||
31 | Update project risks | 3 | 6 | 12 | 7 | √ | ||
32 | Draft risk register | 2 | 3 | 8 | 4 | |||
33 | Finalize risk management plan | 2 | 4 | 7 | 4 | |||
34 | Finalize Project Plan | |||||||
35 | Finalize communications management plan | 2 | 3 | 4 | 3 | |||
36 | Finalize procurement management plan | 2 | 6 | 14 | 7 | |||
37 | Finalize stakeholder management plan | 2 | 2 | 5 | 3 | |||
38 | Finalize project schedule/cost baseline | 2 | 13 | 19 | 12 | |||
39 | Finalize project plan | 2 | 5 | 16 | 6 | √ | ||
40 | Obtain approval for project plan | 2 | 4 | 7 | 4 | √ | ||
41 | Executing | |||||||
42 | Hardware | |||||||
43 | Procure hardware from suppliers | 10 | 24 | 32 | 23 | √ | ||
44 | Software | |||||||
45 | Obtain software OS licenses | 6 | 11 | 20 | 12 | √ | ||
46 | Obtain software application licenses | 6 | 8 | 17 | 9 | |||
47 | Pilot Testing | |||||||
48 | Setup test area | 1 | 2 | 2 | 2 | |||
49 | Load software onto pilot machines | 4 | 6 | 8 | 6 | √ | ||
50 | Validate functionality | 3 | 6 | 8 | 6 | |||
51 | Deployment | |||||||
52 | Configure production hardware | 10 | 25 | 33 | 24 | √ | ||
53 | Deploy production hardware | 11 | 19 | 23 | 18 | √ | ||
54 | Load software to deployed hardware | 12 | 17 | 19 | 17 | √ | ||
55 | Testing | |||||||
56 | Validate startup on deployed hardware | 4 | 9 | 18 | 10 | √ | ||
57 | Perform OS testing | 4 | 8 | 17 | 9 | |||
58 | Perform application testing | 4 | 19 | 28 | 18 | √ | ||
59 | Obtain formal sign-off from users | 6 | 17 | 24 | 16 | |||
60 | Monitoring and Controlling | |||||||
61 | Formal Customer Review 1 | |||||||
62 | Hold formal customer review after project plan approval | 1 | 3 | 4 | 3 | √ | ||
63 | Update project plan | 4 | 10 | 20 | 11 | |||
64 | Formal Customer Review 2 | |||||||
65 | Obtain updates regarding key deliverables from project team | 5 | 18 | 22 | 17 | √ | ||
66 | Hold formal customer review after pilot testing | 5 | 7 | 11 | 7 | √ | ||
67 | Update project plan | 4 | 8 | 15 | 9 | |||
68 | Closing | |||||||
69 | External | |||||||
70 | Finalize procurement with suppliers | 5 | 18 | 24 | 17 | |||
71 | Customer Approval | |||||||
72 | Hold final customer review | 1 | 2 | 2 | 2 | √ | ||
73 | Prepare/submit final customer report | 3 | 6 | 10 | 6 | √ | ||
74 | Audit against contractual deliverables | 3 | 5 | 8 | 5 | |||
75 | Obtain final customer approval | 2 | 3 | 4 | 3 | √ | ||
76 | Internal | |||||||
77 | Hold lessons learned meeting | 1 | 1 | 1 | 1 | |||
78 | Update final internal report | 4 | 6 | 12 | 7 | √ | ||
79 | Hold project team celebration event | 1 | 1 | 2 | 1 | √ | ||
Expected Project Finish Time: | Total Critical Path Variance: | days | ||||||
days | ||||||||
Total Critical Path Standard Deviation: | days | |||||||
Probability of finishing the project in | 287 | days is | ||||||
or | ||||||||
% | ||||||||
Probability of finishing the project in | 273 | days is | ||||||
or | ||||||||
% |
Collepals.com Plagiarism Free Papers
Are you looking for custom essay writing service or even dissertation writing services? Just request for our write my paper service, and we'll match you with the best essay writer in your subject! With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.
Get ZERO PLAGIARISM, HUMAN WRITTEN ESSAYS
Why Hire Collepals.com writers to do your paper?
Quality- We are experienced and have access to ample research materials.
We write plagiarism Free Content
Confidential- We never share or sell your personal information to third parties.
Support-Chat with us today! We are always waiting to answer all your questions.