MPM7004 PRES1 Group Task Ecoviron Protect Centre (EPC) The following fictional case study illustrates how mega and complex i
I must do task 3
AS A PROJECT RISK MANAGER I MUST DETERMINE WHICH TYPE OF CONTRACT IS SUITED FOR THIS GIVEN PROJECT (PRIME CONTACTING OR MULTIPLE CONTRACTING )
Page 1 of 4
MPM7004 PRES1 Group Task
Ecoviron Protect Centre (EPC)
The following fictional case study illustrates how mega and complex infrastructure project,
distinct in project phases and life cycles, must be completed before a project proceeds.
Ecoviron Protect Centre (EPC) – Project Introduction
Ecoviron Protect Centre (EPC) is multi-purpose ecological and environmental project
designated to be built in Conwy area of North Wales – a good site with a minimum of 200 acres.
This allows for structures, parking and gardens. This size of EPC allows for production to be
included in greenhouses or outdoor beds. The EPC allows for removal of storm and surface
water. The EPC project is planned to allow great visibility to attract customers. The appearance
including the buildings, landscaping and plants that are displayed should make a favourable
impression.
It is envisaged that this project aim will be accomplished by expanding to provide transport link
to the northern and southern Wales. Efficient transport systems including rails and roads
installed to be pre-programmed to follow navigational channels accurately and automatically,
and to reduce traffics and ensure value for money for the customers.
Economically, this expansion would attract visitors and spectators from every region of Wales. It
is important that there is considerable access for vehicles. The greater the site line the safer the
egress. If possible, there should also be a slowdown lane to let other vehicles pass. A permit for
highway access is usually required. Some growers have found that setting up a temporary
greenhouse in the parking lot of a shopping centre or mall can give good exposure and
expanded sales. The greenhouse needs to be anchored to resist the strong winds that
frequently affects the structure of the buildings, as well as the need to meet snow load
requirements.
Some auxiliary structures may be considered in designing the hub include plant production
tents, shopping centre or mall, car parks, and cafeteria.
Ecoviron Protect Centre (EPC) – Scope
The Ecoviron Protect Centre (EPC) is one of the Conwy County Council (CCC) projects, which
is due to be fully commissioned in Summer 2022. Currently, the EPC project is undergoing
feasibility development stage. Based on cost-benefit-analysis data and expert opinions, the
CCC Project Development Committee budgeted £6 Billion for successful completion of the
project in 36 months timeline.
The CCC is working on various project requirements and documentations for comprehensive
project planning, project delivery, project completion, project exit and other documents for
project governances and deliverables.
Key project elements of EPC Project include construction of 100 green trees production plants,
multi-storey fresh fruits and vegetable shopping centre, a multi-storey car park, and modern
continental cafeteria. The transport networks and maintenance structures involves constructing
bridges and transport network stations.
Page 2 of 4
Project Implementation
The feasibility team has presented a work breakdown structure (WBS) for the project, which
subdivides the project work into the major project activities. For example, a major element of
work is the mapping of road access and traffic flow to and from the EPC.
The project team is expected to develop the lower tiers of the WBS hierarchy in isolation. This
practice provides flexibility and full control over respective responsibilities:
WBS level 1 – Project: the project’s major construction activities.
WBS level 2 – Project units: the main project packages associated with each project and
subunits within project packages.
WBS level 3 – Contract: the main contracts that can be offered.
WBS level 4 – Contract unit: level of work effort required for the project management
such as agricultural, environmental, engineering and transportation.
The specialist team proposed that once the contracts and contract units are identified, the
project could then be outsourced to different contractors, including, most likely, a consortium.
Project Management
The feasibility team has proposed that a dedicated project management team should be
established within the CCC. The team would have total control over budgets and schedules and
would report directly to the EPC Project Development Committee. The control, planning, and
management of the project present complex logistical issues. The scheme may entail numerous
individual contract packages, which will require coordination.
At a very early stage, the feasibility team settled the key project management objectives as
• effective and efficient communication of information
• utilization of thorough project control techniques
• efficient and widely understood procurement and contractor processes
This standardisation is necessary to ensure that all project teams are working in unison. To furnish timely and accurate cost reports, the project control team needs a comprehensive system that integrates cost and schedule, provides reporting capabilities consistent with the project requirements, and improves operating efficiency.
The system has to be capable of processing and analysing a vast amount of incoming monthly cost data quickly and accurately. In addition, the team could use integrated systems to perform risk and schedule simulation analysis where the relationship between the schedule and cost is not always clear.
Although technology has simplified data collection and scheduling, the feasibility team has identified that professionals must carefully study and analyse the system output to provide a logical, meaningful explanation of the causes of any cost and schedule variances. In this way,
Page 3 of 4
sound project control methodologies reduce cost overruns, control cost growth, help meet project schedule objectives, and ultimately satisfy the client's expectations.
Feasibility Report
The feasibility team completed their study on schedule with an outline of strategy, detailed recommendations, and a list of preferred suppliers, and they are waiting for risk assessment report to be completed, before full commissioning of the project. The main outcomes from the team are the following:
• Contractor participation is a key aspect to the success of the project, and the CCC should establish and work with a set of preferred suppliers.
• The CCC Project Development Committee should establish a detailed project management office that has the authority to manage and control the project and report to senior government officials.
• The risk assessment team should determine the probability of various cost outcomes and quantify the required contingency needed in the cost estimate and delivery schedule to achieve any desired level of cost confidence.
Ecoviron Protect Centre – Assignment Tasks
Task 1: Risk Management Plan
As clearly stated in the Assignment Brief above, the EPC is waiting to be fully commissioned in
the Summer 2022, and project is at the initiation stage. You are part of the assembled dedicated
risk management team (including risk manager, risk analyst, risk auditor). The first set of tasks
entails identifying a risk management plan, including Risk Register for consideration to inform
key decisions by the project funder – the CCC.
Step 1: Prepare the risk management plan.
Step 2: In each section of the plan, provide the detail of what should be considered e.g.in the
‘methodology’ section…
• risk identification with explanation on how it will be completed
• risk analysis (qualitative and quantitative analysis) with explanation on how it will be
completed
Step 3: Highlight areas that you feel, as a member of risk management team, are critical to the
success of the project.
Task 2: Risk Gathering Techniques
As part of the risk management team that completed Task 1 and have delivered a risk
management plan. Funder has requested that a relevant analysis, using tools (e.g., SWOT,
PESTLE, etc.) be performed to ensure that your team have captured all potential risks and
issues required for a successful EPC project delivery.
Using Risk Identification Tools and Techniques: You have completed the PESTLE analysis and
there are some apparent risks that need to be logged. You are tasked with putting a risk
response plan together that will present
• risk event
• risk consequence
Once completed, you are required to identify potential risk responses.
Page 4 of 4
Task 3: Decision Tree
The CCC is looking at construction contracts options to minimise cost associated with project
failures (based on historical risk report). Decision needs to be made on whether the project
would be constructed under multiple contractors or multiple subcontractors. One option is to go
for a prime contractor with multiple contracts. The other option is to use multiple contractors for
agreed or limited number of contracts.
First option, which is a prime contractor with multiple contracts, estimated to cost £4.5 billion, is
controllable and entails direct relationship and monitoring, but is liable to ‘one throat to choke’ –
if prime contractor fails, the project is likely to fail. The probability of this occurring is 35% with
estimated cost of £150 million over the 36 months of operation.
Second option, which is use of multiple contractors for different projects, cost estimated £4
billion, with 25% probability of saving the CCC £100 million at the completion of the project.
These savings are associated with success and reliability rating of the contractors. As a
dedicated risk management professional, which option would you recommend? Use a decision
tree to determine the best alternative.
Task 4: Detailed Risk Analysis
In this task, you have a list of some apparent risks that need to be logged. You are tasked with
putting a risk response plan together to analyse each of the risks
• Responding to Analysed Risk
• Put a risk response plan together that includes an analysis and response strategy for each risk.
Use the headings
• avoidance
• mitigation
• transference
• acceptance
Task 5: Risk Response Plan
Present the full completed version of the risk response template
Collepals.com Plagiarism Free Papers
Are you looking for custom essay writing service or even dissertation writing services? Just request for our write my paper service, and we'll match you with the best essay writer in your subject! With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.
Get ZERO PLAGIARISM, HUMAN WRITTEN ESSAYS
Why Hire Collepals.com writers to do your paper?
Quality- We are experienced and have access to ample research materials.
We write plagiarism Free Content
Confidential- We never share or sell your personal information to third parties.
Support-Chat with us today! We are always waiting to answer all your questions.