Question 1
Each of the following is an element of the cost management plan except which one?
Level of accuracy
Reporting formats
Units of measure
Cost aggregation method
Question 2
Which of the following is used during the Project Cost Management Knowledge Area to monitor and control project costs? It is used to calculate earned value performance measures and consists of factors such as actual cost, schedule, and scope.
Control account
Code of accounts
Chart of accounts
Control thresholds
Question 3
All of the following are true regarding the Determine Budget process except:
It assigns cost estimates to the project activities.
The cost baseline plots the sum of estimated costs in a linear graph.
Estimates in the cost baseline are used to measure variances and performance later in the project.
The cost baseline, once established, is the expected cost for the project.
Get a plagiarism-free answer to this question
Send us your instructions and we’ll match you with the best writer in your subject.
- 100% human-written, zero AI
- Turnitin report included
- Confidential — we never share your data
- Free revisions & refunds