Question 1
When completing a forward pass, you carry the early finish to the next activity where it becomes its early start unless the next succeeding activity is a merge activity. In this case you select the smallest early finish number of all its immediate predecessor activities.
A. True
B. False
Question 2
________ activities are to be completed immediately following a particular activity.
A. Parallel
B. Successor
C. Merge
D. Burst
E. Predecessor
Question 3
An activity cannot begin until ALL preceding connected activities have been completed.
A. True
B. False
Question 4
Which of the following correctly calculates the late start for an activity?
A. LF – SL
B. ES – DUR
C. ES – SL
Get a plagiarism-free answer to this question
Send us your instructions and we’ll match you with the best writer in your subject.
- 100% human-written, zero AI
- Turnitin report included
- Confidential — we never share your data
- Free revisions & refunds