Scheduling
For an organization, the following project schedule is given. Assume that all times are in days.
Task |
Predecessor |
Normal Time |
Crash Time |
Crash Cost Slope (per day) |
A |
None |
7 |
7 |
NA |
B |
A |
3 |
3 |
NA |
C |
A |
8 |
4 |
600 |
D |
A |
4 |
4 |
NA |
E |
B |
6 |
5 |
600 |
F |
C, D |
2 |
2 |
NA |
G |
E, F |
6 |
6 |
NA |
H |
F |
5 |
3 |
400 |
I |
G, H |
4 |
4 |
NA |
J |
I |
2 |
2 |
NA |
Address the following:
- Draw the AON project network using Microsoft Project, Microsoft Visio, or some other tool capable of creating such a network. Perform a critical path analysis for the network and calculate the ES, EF, LS, and LF times.
- Calculate the slack time for each activity.
- Identify the critical path(s).
- Assume that the organization will receive a $400 bonus for each day the duration of the project is shortened. The organization is also responsible for paying the crash cost associated with shortening the schedule. To maximize the net profit, identify which task you should crash and by how much.
Collepals.com Plagiarism Free Papers
Are you looking for custom essay writing service or even dissertation writing services? Just request for our write my paper service, and we'll match you with the best essay writer in your subject! With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.
Get ZERO PLAGIARISM, HUMAN WRITTEN ESSAYS
Why Hire Collepals.com writers to do your paper?
Quality- We are experienced and have access to ample research materials.
We write plagiarism Free Content
Confidential- We never share or sell your personal information to third parties.
Support-Chat with us today! We are always waiting to answer all your questions.