The questions are the 12 questions:1. Using our understandin
The questions are the 12 questions:1. Using our understanding of ‘Project Cost Management’ Data Analysis, select the ONE CORRECT description of the following phrase:This is the total cost incurred in accomplishing the work.A) Earned Value Management (EVM)B) Earned Value (EV)C) Earned Value (EV)D)Actual Cost (AC)2. Looking at Figure 7-12 in the textbook and using the ‘Data Date’ that they have indicated with the vertical line, select the ONE CORRECT answer regarding the example project SCHEDULE.A) The earned value has caused the project to be ahead of schedule at this point.B) The SPI cannot be calculated for this example since there are no numbers to conduct the mathematical problem.C) The project will absolutely over run the total schedule if the current burn rate continues.D) The project will absolutely under run the total schedule [e.g. come in ahead of schedule] if the current burn rate continues.E) If you could calculate the SPI value, it would indicate that at that particular moment in time, the project is behind schedule.3. Using our understanding of ‘Project Cost Management’, select the ONE CORRECT description of the following phrase: This is the process of aggregating the estimated costs of individual activities to establish a cost baseline.Estimate CostsControl BudgetControl CostsDetermine CostsPlan Cost ManagementControl EstimatesDetermine Budget4. Using our understanding of ‘Project Cost Management’ Data Analysis, select the ONE CORRECT description of the following phrase: This is the budget associated with the work that has been completed.Earned Value (EV)Earned Value Management (EVM)Actual Cost (AC)Planned Value (PV) 5. Using our understanding of ‘Project Cost Management’, select the ONE CORRECT description of the following phrase: This is the process of developing an approximation of the money needed to complete the project work.Determine BudgetControl CostsEstimate CostsControl EstimatesDetermine CostsPlan Cost ManagementControl Budget6. Using our understanding of ‘Project Cost Management’, select the ONE CORRECT description of the following phrase: This is the process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled.Plan Cost ManagementDetermine CostsControl BudgetEstimate CostsControl CostsDetermine BudgetControl Estimates7. Using our understanding of ‘Project Cost Management’, select the ONE CORRECT description of the following phrase: This is the MOST important task within the ‘Project Cost Management’ activities.Control CostsDetermine BudgetDetermine CostsEstimate CostsControl EstimatesPlan Cost ManagementControl Budget8. Looking at Figure 7-12 in the textbook and assuming the ‘Data Date’ (vertical) line represents ‘Today’s Date’, select the ONE CORRECT answer regarding the example project COST.The project will absolutely under run the total costs if the current burn rate continues.If you could calculate the CPI value, it would indicate that at that particular moment in time, the project indicates a cost overrun.The earned value has caused the project to be under-budget at this point.The project will absolutely over run the total costs if the current burn rate continues.The CPI value cannot be calculated for this example since there are no numbers to conduct the mathematical problem.Using our understanding of ‘Project Cost Management’, select the ONE CORRECT description of the following phrase:9. This is the ONLY ‘Project Cost Management’ activity that has ONLY ONE output.Estimate CostsDetermine BudgetControl CostsPlan Cost ManagementControl BudgetControl EstimatesDetermine Costs10. Looking at Figure 7-12 in the text, identify the ONE CORRECT answer listed here.As of this point in time, this is NOT a successful project from a financial perspective.The total health of this project cannot be determined since we do not know if we met the project schedule.The project that this diagram represents never went over budget during the course of the project.This was a successful project from a financial perspective.Using our understanding of ‘Project Cost Management’, select the ONE CORRECT description of the following phrase:11. This is the ONLY ‘Project Cost Management’ activity that is NOT performed during the ‘Planning Process.’Control EstimatesControl CostsEstimate CostsControl BudgetDetermine BudgetPlan Cost ManagementDetermine Costs12. Using our understanding of ‘Project Cost Management’ Data Analysis, select the ONE CORRECT description of the following phrase: This is the budget planned for the work to be accomplished.Planned Value (PV)Earned Value Management (EVM)Earned Value (EV)Actual Cost (AC)
Collepals.com Plagiarism Free Papers
Are you looking for custom essay writing service or even dissertation writing services? Just request for our write my paper service, and we'll match you with the best essay writer in your subject! With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.
Get ZERO PLAGIARISM, HUMAN WRITTEN ESSAYS
Why Hire Collepals.com writers to do your paper?
Quality- We are experienced and have access to ample research materials.
We write plagiarism Free Content
Confidential- We never share or sell your personal information to third parties.
Support-Chat with us today! We are always waiting to answer all your questions.
