In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project.

Uncategorized

Use the Week 5 Exercises Template attached here to complete this assignment.

Click on each of the tabs in the template to view and complete each of the exercises

Thanks

  • attachment

    PMT4725-2Assignment-Week5ExercisesTemplate.xlsx

Ch 13 Ex 1

PMT472 5.2 ASSIGNMENT: WEEK 5 EXERCISES
CH. 13 EXERCISE 1
In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project.
NOTE: SV = EV – PV; CV = EV – AC
Actual Cost (AC) (given) (Enter value)
Earned Value (EV) (given) (Enter value)
Planned Value (PV) (given) (Enter value)
Schedule Variance (SV) (Type Excel formula to calculate result)
Cost Variance (CV) (Type Excel formula to calculate result)

Ch 13 Ex 2

PMT472 5.2 ASSIGNMENT: WEEK 5 EXERCISES
CH. 13 EXERCISE 2
On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project.
NOTE: CPI = EV / AC
Actual Cost (AC) (given) (Enter value)
Earned Value (EV) (given) (Enter value)
Planned Value (PV) (given) (Enter value)
Schedule Variance (SV) (Type Excel formula to calculate result)
Cost Variance (CV) (Type Excel formula to calculate result)
Cost Performance Index (CPI) (Type Excel formula to calculate result)
What is your assessment of the project on day 51?
(Enter response)

Ch 13 Ex 3

PMT472 5.2 ASSIGNMENT: WEEK 5 EXERCISES
CH. 13 EXERCISE 3
Given the following project network and baseline information, complete the form to develop a status report for the project at the end of period 4 and the end of period 8.
NOTE: EV = Actual % Complete * total PV budget for that task. Do not use time-phased PV in this formula.
Status Report: Ending Period 4
Task Actual % Complete EV AC PV CV SV
A 100% 400 300 400 100 0
B 50% 1200 1000 800 200 400
C 33% 495 500 600 -5 -105
D 0% 0 0 0 0 0
E 0% 0 0 0 0 0
F 0% 0
Cumulative Totals 2095 1800 1800 295 295
The first one has been done as an example. At the end of period 4, the project is $300 under budget and $300 ahead of schedule.
Status Report: Ending Period 8
Task Actual % Complete EV AC PV CV SV
A 100% 300 400
B 100% 2200 2400
C 100% 1500 1500
D 25% 300 0
E 33% 300
F 0% 0
Cumulative Totals 0 4600 4300 0 0
From the data you have collected and computed for periods 4 and 8, what information are you prepared to tell the customer about the status of the project at the end of period 8?
(Enter response)

Ch 13 Ex 4

PMT472 5.2 ASSIGNMENT: WEEK 5 EXERCISES
CH. 13 EXERCISE 4
Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8 and complete the performance indexes table. Calculate the EACf and the VACf.
NOTE: Scheduling Performance Index SPI = EV / PV; Percent Complete Index Budgeted Costs PCIB = EV / BAC; Budgeted Cost at Completion BAC = total PV for whole project; Estimated Cost at Completion EACf = ((BAC – cumulative total EV)/(cumulative total EV/cumulative total AC)) + cumulative total AC; Cost Variance at Completion VACf = BAC – EACf.
Status Report: Ending Period 2
Task Actual % Complete EV AC PV CV SV
A 75% 25
B 50% 12
C 0% 0
D 0% 0
E 0% 0
F 0% 0
Cumulative Totals 0 37 0 0 0
Status Report: Ending Period 4
Task Actual % Complete EV AC PV CV SV
A 100% 35
B 100% 24
C 0% 0
D 0% 0
E 0% 0
F 0% 0
Cumulative Totals 0 59 0 0 0
Status Report: Ending Period 6
Task Actual % Complete EV AC PV CV SV
A 100% 35
B 100% 24
C 75% 24
D 0% 0
E 50% 10
F 0% 0
Cumulative Totals 0 93 0 0 0
Status Report: Ending Period 8
Task Actual % Complete EV AC PV CV SV
A 100% 35
B 100% 24
C 100% 32
D 33% 20
E 100% 20
F 0% 0
Cumulative Totals 0 131 0 0 0
Performance Indexes Summary
Period EV AC PV SPI CPI PCIB
2
4
6
8
Estimate at Completion (forecasted) (EACf) (Type Excel formula to calculate result)
Cost Variance at Completion (forecasted) (VACf) (Type Excel formula to calculate result)
Based on your data, what is your assessment of the current status of the project? At completion?
(Enter response)

Ch 13 Ex 5

PMT472 5.2 ASSIGNMENT: WEEK 5 EXERCISES
CH. 13 EXERCISE 5
Given the following project network, baseline, and status information, develop status reports for periods 1–4 and complete the project summary graph. Report the final SV, CV, CPI, and PCIB at the end of period 4.
Status Report: Ending Period 1
Task Actual % Complete EV AC PV CV SV
1 50% 6 4
2 40% 8 3
3 25% 3
4 0% 0
5 0% 0
6 0% 0
7 0% 0
Cumulative Totals 0 17 7 0 0
Status Report: Ending Period 2
Task Actual % Complete EV AC PV CV SV
1 100% 13
2 80% 14
3 75% 8
4 0% 0
5 0% 0
6 0% 0
7 0% 0
Cumulative Totals 0 35 0 0 0
Status Report: Ending Period 3
Task Actual % Complete EV AC PV CV SV
1 100% 12 13
2 80%

Collepals.com Plagiarism Free Papers

Are you looking for custom essay writing service or even dissertation writing services? Just request for our write my paper service, and we'll match you with the best essay writer in your subject! With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.

Get ZERO PLAGIARISM, HUMAN WRITTEN ESSAYS

Why Hire Collepals.com writers to do your paper?

Quality- We are experienced and have access to ample research materials.

We write plagiarism Free Content

Confidential- We never share or sell your personal information to third parties.

Support-Chat with us today! We are always waiting to answer all your questions.

Chapter 9 Case Study: ?Nightingale Project Part A & Part B Background Write personal purpose statements using the Purpose Principle?

Related Posts

Uncategorized

How to Write an Introduction for an Essay That Grabs the Marker

Uncategorized

How to Write a Thesis Statement: Complete Guide with Examples

Uncategorized

Can an Essay Writing Service Help You Meet a Tight Deadline?

Why Choose Us

How Our Website Works

Get an Essay from Us

Our writers will help you write all your homework. They will write your papers from scratch.We also have a team of editors who read each paper from our writers just to make sure all papers are of HIGH QUALITY& PLAGIARISM FREE. WE DO NOT USE AI when writing PAPERS.

Step 1
To make an Order you only need to click Place Order and we will direct you to our Order Page. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline. Deadline range from 6 hours to 30 days.

Step 2
Once done with writing your paper we will upload it to your account on our website and also forward a copy to your email.

Step 3
Upon receiving your paper, review it and if any changes are needed contact us immediately. We offer unlimited revisions at no extra cost.

Is it Safe to use our services?
We never resell papers on this site. Meaning after your purchase you will get an original copy of your assignment and you have all the rights to use the paper.

Pricing and Discounts
Our price ranges from $8-$14 per page. If you are short of Budget, contact our Live Support for a Discount Code. All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.
Please note we do not have prewritten answers. We need some time to prepare a perfect essay for you.

Recent Posts

  • Scenario: A Country Facing a Food Crisis
  • Write a professional email to a person you consider revolutionary in your chosen field of study or career field
  • Scenario: A Country Facing a Food Crisis
  • Write a professional email to a person you consider revolutionary in your chosen field of study or career field
  • Analyse a marketing decision where a firm operating across borders faced an ethical problem that a single-market firm would not have faced
College Pal

All Rights Reserved Terms and Conditions
College pals.com Privacy Policy 2010-2018