When completing a forward pass, you carry the early finish to the next activity where it becomes its early start unless the next succeeding activity is a merge activity. In this case you select the smallest early finish number of all its immediate predecessor activities.
Question 1 When completing a forward pass, you carry the early finish to the next activity where it becomes its early start unless the next succeeding activity is a merge activity. In this case you select the smallest early finish number of all its immediate predecessor activities.
• Question 2 ________ activities are to be completed immediately following a particular activity.
• Question 3 An activity cannot begin until ALL preceding connected activities have been completed.
• Question 4 Which of the following correctly calculates the late start for an activity?
Question 5 Which of the following is true about hammock activities?
• Question 6 Which of the following will correctly calculate the total slack in an activity?
• Question 7 ________ activities must be completed immediately before a particular activity.
• Question 8 A merge activity is one that merges with other activities into a succeeding activity.
• Question 9 Which of the following is provided by both the project network and the work breakdown structure?
• Question 10 If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a
• Question 11 The critical path is the shortest path through a network and indicates activities that cannot be delayed without delaying the project.
• Question 12 If a network has more than one critical path but noncritical activities have very little slack, the network is considered to have a high level of sensitivity.
• Question 13 The likelihood the original critical path(s) will change once the project is initiated is referred to as
• Question 14 If the project has a duration of 13 days, the project should be completed 13 days from the day it starts.
• Question 15 An activity that has more than one dependency arrow flowing into it is termed a(n)
• Question 16 When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select
• Question 17 The amount of time an activity can be delayed and yet not delay the project is termed
• Question 18 The backward pass in project network calculations determines all of the following EXCEPT
• Question 19 Which of the following correctly calculates the early finish for an activity?
• Question 20 The minimum amount of time a dependent activity must be delayed to begin or end is referred to as
• Question 21 Lags can be used to constrain the start and finish of an activity.
• Question 22 Arrows on an activity-on-node (AON) project network represent
• Question 23 Activities which can take place at the same time are termed
• Question 24 Experience suggests that when there are multiple starts, a common start node should be used to indicate a clear project beginning on the network. Similarly, a single project end node can be used to indicate a clear ending.
• Question 25 Gantt charts are popular because they represent an easy-to-understand, clear picture on a time-scaled horizon.
Collepals.com Plagiarism Free Papers
Are you looking for custom essay writing service or even dissertation writing services? Just request for our write my paper service, and we'll match you with the best essay writer in your subject! With an exceptional team of professional academic experts in a wide range of subjects, we can guarantee you an unrivaled quality of custom-written papers.
Get ZERO PLAGIARISM, HUMAN WRITTEN ESSAYS
Why Hire Collepals.com writers to do your paper?
Quality- We are experienced and have access to ample research materials.
We write plagiarism Free Content
Confidential- We never share or sell your personal information to third parties.
Support-Chat with us today! We are always waiting to answer all your questions.